What a main fuse allows
The main fuse (huvudsäkring) limits how much current your house can draw from the grid at once. Swedish houses almost always have a three-phase supply. Available power is 3 × 230 V × current:
| Main fuse | Total power (theoretical) | per phase |
|---|---|---|
| 16 A | approx. 11 kW | 3.7 kW |
| 20 A | approx. 13.8 kW | 4.6 kW |
| 25 A | approx. 17.3 kW | 5.75 kW |
| 35 A | approx. 24.2 kW | 8.05 kW |
The "per phase" column is the important one: a single-phase appliance such as an oven or kettle only loads one phase. If several large single-phase appliances share a phase, the fuse trips even though total power would be enough. A fuse tolerates brief overloads, but plan with these figures.
Adding up your power demand
Typical figures for the big loads in a new build – what counts is always the rating plate or data sheet of your own appliance:
| Load | Typical power | Controllable? |
|---|---|---|
| Three-phase EV charger | 11 kW (3 × 16 A) | Yes, charging power can be reduced |
| Ground-source or air-to-water heat pump | compressor a few kW, immersion heater several kW on top (often in steps up to approx. 9 kW) | Partly: limit the immersion heater, shift hot water |
| Induction hob | up to approx. 7–11 kW, rarely at full power | No |
| Oven | 2–3.5 kW | No |
| Sauna heater | 6–9 kW | Hardly |
| Water heater | approx. 3 kW | Yes, can be shifted in time |
| Washing machine, dryer, dishwasher | approx. 2 kW each while heating | Yes, start time |
| Base load (ventilation, fridge, network, lighting) | 0.5–1 kW | No |
The rating plates easily add up to 40 kW – which would mean 63 A. But everything never runs at once. What matters is the worst realistic moment. How much a heat pump in northern Sweden relies on its immersion heater in frost is covered in Heat pumps in northern Sweden. A worked example for a cold January evening at 6 pm:
- Heat pump with immersion heater in frost: 3 kW + 6 kW = 9 kW
- Cooking: 5 kW
- Base load: 1 kW
- Subtotal: 15 kW – fits within 25 A if the phases are evenly loaded.
- The car comes home and starts charging at 11 kW: 26 kW – not even 35 A is enough.
The answer is not automatically a bigger fuse but control: the charger throttles while you cook and charges fully at night, and the hot water isn't heated at exactly 6 pm. Then 20 or 25 A is plenty in many houses. I have a 20 A main fuse myself and regulate the charging power of my home battery exactly so that it doesn't trip.
What a bigger fuse costs
Swedish grid fees usually consist of a fixed fee that rises with fuse size plus a price per kilowatt-hour. Two examples from the 2026 price lists:
| Main fuse | Sundsvall Elnät (fixed fee per year) | Ellevio (fixed fee per year, from 1 June 2026) |
|---|---|---|
| 16 A | SEK 5,189 | SEK 5,400 |
| 20 A | SEK 8,053 | SEK 7,080 |
| 25 A | SEK 10,928 | SEK 8,880 |
| 35 A | SEK 15,056 | SEK 13,560 |
Prices include VAT; Ellevio's are calculated from monthly prices. On top comes the transmission fee per kWh, which at both operators is the same for every fuse size (Sundsvall Elnät 26.3 öre, Ellevio 26.0 öre), plus energy tax. E.ON and other operators have their own price lists – check the one for the area where you build.
What it means: at Sundsvall Elnät, 35 A costs about SEK 4,100 more per year than 25 A – over SEK 41,000 in ten years. Even going from 20 to 25 A costs almost SEK 2,900 a year. Load balancing for the charger is nearly always cheaper; compare its quoted price with these amounts.
About the change itself: only an authorised electrician may change the main fuse, and they must notify the grid operator in writing. Many operators allow a tariff change at most once a year, and if you raise the connection above the size the connection fee was paid for, an additional connection fee may apply. Sundsvall Elnät only quotes new connections from 35 A upwards on request. In a new build it pays to work out the size before applying for the connection.
Capacity charges: the situation in October 2026
For a long time it looked as if every grid operator would have to introduce a capacity charge (effektavgift) by 2027, billing you for your highest monthly peaks. The government stopped that requirement in March 2026. Ellevio has been billing by fuse size again since 1 June 2026, E.ON has paused its planned introduction, and Sundsvall Elnät's 2026 price list for households contains no capacity charge.
That may change again. A house whose large loads can be controlled is ready for both models: with a fuse-based tariff you save through a smaller fuse, with a capacity charge through low peaks.
Load balancing for the EV charger
A charger with load balancing continuously measures the house's consumption and reduces charging power before the main fuse reaches its limit. It measures either with its own meter in the consumer unit or via the electricity meter's HAN port, which the grid operator has to activate.
One step further is shared control, for example in Home Assistant: it decides who goes first – heat pump, hot water, car or battery – and also charges the car in the cheapest hours. What the right charging time alone saves is in Charging an EV at home in Sweden: what the right time saves.
Installing an EV charger qualifies for the green technology tax reduction of 50 percent of labour and materials if the charging point supplies your own household – according to Skatteverket, also on a house under construction.
Meter cabinet and consumer unit: room for the future
The consumer unit fills up quickly in a new build: lighting and socket circuits, cooker, heat pump, ventilation, EV charger, residual current devices. Anyone adding solar panels, a battery, a sauna or a garden building later needs free spaces. Ask the electrician to:
- leave spare ways in the consumer unit and state in the quote how many remain free,
- install the EV charger circuit with the appropriate residual current protection now, even if the car comes later,
- leave space for an energy meter or load monitor and for surge protection,
- spread the phases so large single-phase loads don't end up on the same phase,
- plan a conduit into the house for the HAN port cable if the meter cabinet is on the outside wall.
Conduit for solar, battery and garage
I don't have solar panels yet, but I do run an inverter with a large battery. The lesson from that: cable routes are the hard part, not the technology. In a new build an empty conduit costs almost nothing:
- From roof or loft to the plant room: generously sized conduit for the panels' DC cables. Plan the inverter location, with wall space and ventilation.
- To the garage, carport or parking space: conduit or the cable itself for the EV charger, even if it comes later. A network cable in the same trench saves a second trench – see Connecting an outbuilding.
- For a battery: a frost-free, dry place outside bedrooms, with clearances and fire protection as specified by the manufacturer. Lithium iron phosphate batteries usually cannot charge, or only to a limited extent, below 0 °C – a cold garage in Norrland is not a good spot.
- Network cable to inverter, battery and charger: control and monitoring then run locally and more reliably than over Wi-Fi.
Solar later: what matters when connecting
A system up to 43.5 kW with a main fuse of at most 63 A counts as micro-production; Sundsvall Elnät charges no extra annual fee for it. The electrician notifies the grid operator before the system is connected. In 2026 the green technology tax reduction is 15 percent for solar panels and 50 percent for a battery storing electricity from your own panels – together with the EV charger, at most SEK 50,000 per person per year. A battery without your own solar panels gets no green technology reduction.
Who does what
Mains wiring, meter cabinet, consumer unit and main fuse are the job of an electrical installation company registered with Elsäkerhetsverket – you can check this with its "Kolla elföretaget" service. I am not an electrician and don't carry out this work. I calculate your power demand with you, compare fuse sizes with your grid operator's fees, write a requirements list for the electrician, and afterwards set up load balancing, price-based control and monitoring – in English, Swedish or German.
Checklist before applying for a connection
- List all large loads with power from the data sheets, today and in ten years (car, heat pump, sauna, solar, battery).
- Work through the worst realistic moment, with and without load balancing.
- Your grid operator's price list: fixed fee per fuse size, capacity charge yes/no, connection fee.
- Plan an EV charger with load balancing; ask the grid operator to activate the HAN port.
- Spare ways in the consumer unit and surge protection in the electrical quote.
- Conduit to roof, garage and from the meter cabinet into the house; network cable to inverter, battery and charger.
- Space for inverter and battery: frost-free, dry, not in the sleeping area.
Frequently asked questions
Is 16 A enough for a new house with heat pump and EV?
Sometimes, but it is tight. With load balancing and night-time charging it can work. Usually 20 or 25 A is a sensible compromise. Work through the worst realistic moment, not the sum of the rating plates.
What does it cost to raise the main fuse later?
Two items: the electrician's work and a higher fixed fee from the grid operator. At Sundsvall Elnät, 25 instead of 20 A costs about SEK 2,900 more per year in 2026. If you go above the size the connection fee was paid for, an additional connection fee may apply.
Should I expect a capacity charge?
The requirement was stopped in March 2026. Ellevio has billed by fuse size again since June 2026, E.ON has paused its introduction, and Sundsvall Elnät has no capacity charge for households in 2026. That may change, and a house with controllable loads is ready for both models.
Can I install the EV charger or conduit myself?
The charger and everything in the meter cabinet and consumer unit may only be done by a registered electrical installation company. Empty conduit without cables is normally not considered electrical installation, but agree route and size with the electrician.
No affiliate links. Recommendations are based purely on hands-on experience.
Building and don't want to pick the main fuse by gut feeling? With the Check plus Connection new build at a fixed price of SEK 2,500 (about 2.5 hours, private customers incl. VAT, credited against follow-up work) I calculate your power demand, compare fuse sizes with your grid operator's fees and write a list for the electrician: load balancing, spare ways and conduit for solar, battery and EV charger. For existing homes, the energy check for SEK 500 is a good first step. A registered electrician carries out the installation.
Energy check and smart energy control Book a free callExternal sources:
- Sundsvall Elnät: fuse subscription for households 2026 (Swedish)
- Sundsvall Elnät: grid connection and micro-production (Swedish)
- Ellevio: fuse subscription from 1 June 2026 (PDF, Swedish)
- VB Energi: 2026 price sheet, connection fee when increasing (PDF, Swedish)
- Energiföretagen: capacity tariff requirement stopped (March 2026, Swedish)
- Byggahus: E.ON pauses capacity charge (Swedish)
- Skatteverket: green technology tax reduction (Swedish)
- Elsäkerhetsverket: check an electrical company (Swedish)